Joint Site Walkover with HK Electric Distribution Planning Department — Sheung Wan Landing No. 1
Identify nearest HKE LV Pillar / Shun Tak perimeter switchroom and measure cable trench distance to Landing No. 1 apron.
Confirm maximum continuous kW/Amp load available immediately from existing local transformer without major roadworks.
Confirm suitability of fixed concrete seawall apron behind Landing No. 1 for customer IP66 meter/isolator pillar (+5.0mPD flood clearance).
Assess option to reserve spare cable ducts during upcoming Chung Kong Rd / waterfront works for Phase 3 (1.5–3.0 MW).
| Pier / Waterfront Node | Deployment Phase & Vessel | Continuous HKE Grid Draw | On-Berth BESS & DC Output | Strategic Role & Route Scope |
|---|---|---|---|---|
| 1A. Sheung Wan Landing No. 1 (Phase 1–2 Pilot) | Phase 1–2: BAYWING-D2 (25-Pax) | 250 kW → 900 kW LV (380V AC) | 400 kWh – 1.2 MWh BESS / 500 kW DC | Public landing validation of HKE LV-to-BESS demarcation & intra-city pilot trials |
| 1B. Sheung Wan / HK–Macau Terminal (Phase 3) | Phase 3: BAYWING EF-150 (150-Pax) | 1.5 MW – 3.0 MW (11kV HV / Dual TX) | 4.0 MWh BESS / 3.5 MW MCS Arm | 20-min turnaround for cross-boundary HK–Macau & GBA high-speed routes |
| 2. Central Piers (Pier 7–10 Corridor) | Phase 2: BAYWING-D2 Fleet | 250 kW – 500 kW LV (380V AC) | 500 kWh BESS / 500 kW DC Fast Charge | High-frequency ultra-short cross-harbour & outlying island commuter routes |
| 3. Wan Chai Ferry Pier Waterfront | Phase 2: BAYWING-D2 Fleet | 250 kW – 500 kW LV (380V AC) | 500 kWh BESS / 500 kW DC Fast Charge | Cross-harbour & East Harbour zero-emission commuter network |